SmartBatt Energy Solutions
← All case studies
Construction·6-Month Deployment · Navi Mumbai

24×7 Power, Lower Cost, Zero Downtime

How a JNPA warehouse construction site cut energy costs by ~20% and gained round-the-clock power — by pairing a smaller DG with a SmartBatt BESS unit.

📍 JNPA, Navi Mumbai🏗️ Warehouse Construction🗓️ 6-Month Deployment🏠 6–7 Porta Cabins
SmartBatt co-founders at the JNPA site — SmartBatt unit installed alongside the 30 KVA diesel generator

SmartBatt co-founders at the JNPA site — the 20kW/40kWh BESS unit (IP65-rated, centre) installed outdoors alongside the 30 KVA diesel generator (left). No shelter or enclosure required.

24×7

Power Availability

vs. 12–14 hrs before

~20%

Monthly Cost Saving

vs. 62 KVA DG alone

3.5 T

CO₂ Avoided

over 6-month deployment

−25%

DG Runtime Reduced

10 hrs/day vs. 12–14 hrs

Client Context

A leading infrastructure contractor was building a large warehousing facility at Jawaharlal Nehru Port (JNPA), Navi Mumbai — one of India's busiest logistics hubs. The project site comprised six to seven porta cabins serving as site offices, workstations for engineers, meeting rooms, a pantry, toilets, and a storage unit.

With no grid connection and no solar infrastructure on site, a 62 KVA diesel generator was the sole power source — running 12 to 14 hours a day. After 9–10 PM, the site went completely dark: a meaningful operational and security concern for a live construction project running over multiple months.

The Challenge

No grid power on site

The site depended entirely on a 62 KVA diesel generator — with full exposure to fuel price volatility, supply logistics, and operator availability.

Limited operating hours

The DG ran from 8 AM to 9–10 PM. After that, the site had no power — no lighting, no CCTV, no connectivity.

Overnight security risk

Cameras and perimeter lighting went offline every night, leaving a large construction site completely unmonitored through the dark hours.

Oversized and inefficient DG

A 62 KVA generator was substantially oversized for the site's average load, running at low utilisation for much of the day — burning fuel inefficiently.

Peak load stress mid-afternoon

When ambient temperatures peaked and air-conditioning loads surged across multiple cabins simultaneously, the DG was pushed to capacity with limited headroom.

Emissions and noise in a working environment

Continuous diesel combustion over 12–14 hours contributed to on-site air quality degradation and noise in an occupied office environment.

The SmartBatt Solution

SmartBatt conducted an on-site power audit to map the load profile across the day. Based on this, the 62 KVA DG was replaced with a 30 KVA unit, and a SmartBatt 20 kW / 40 kWh BESS unit was deployed alongside — coordinated in a charging and peak-shaving cycle through the day.

IP65 Rated for Outdoor Deployment — The SmartBatt unit is fully protected against dust ingress and water jets, making it suitable for open-air installation with no additional shelter or enclosure required. At the JNPA site, the unit was mounted outdoors directly alongside the DG.

Daily Operating Cycle

9 AM – 12 PM

DG: ON (30 KVA)

Charging

DG powers cabins at low morning load while simultaneously charging the SmartBatt unit.

12 PM – 5 PM

DG: ON (30 KVA)

Peak Shaving

As AC loads surge in the afternoon heat, SmartBatt supplements the DG — handling demand the 30 KVA unit alone couldn't support.

5 PM – 6 PM

DG: ON (30 KVA)

Re-charging

As load eases toward evening, the DG re-charges the battery to prepare for the overnight window.

6 PM – 9 AM (next day)

DG: OFF

Overnight on Battery

The entire site load — CCTV, perimeter lighting, fans, refrigerator — runs on SmartBatt for 15 uninterrupted hours. DG is silent.

The DG ran for only 10 hours per day — and was off entirely from 6 PM to 9 AM — while the site maintained uninterrupted power throughout the night.

How Peak Shaving Works

As-Is — 62 KVA DG only

As-is load profile: 62 KVA diesel generator handling all site load

Proposed — 30 KVA DG + SmartBatt

To-be load profile: 30 KVA DG with SmartBatt peak shaving and overnight battery supply

Equipment Powered

Split air-conditioners across offices, meeting rooms, and workstations
LED lighting throughout all cabins and external perimeter lights — 24 hrs
Laptops, monitors, chargers, printers at all workstations
Pantry appliances — microwave, coffee machine, refrigerator
CCTV security cameras and network equipment — operational overnight

Before vs. After

Cost figures are directional. Actual savings vary based on diesel prices, DG vendor terms, and site-specific load profile.

ParameterBeforeAfterChange
DG Size62 KVA30 KVA52% smaller DG
Power Availability12–14 hrs/day24 hrs/day (continuous)Full coverage
DG Runtime12–14 hrs/day10 hrs/day~25% less DG use
Fuel Consumption~4 L/hr~3 L/hr~220 L/month saved
Monthly Energy CostHigher baseline~15–20% lowerNet cost saving
Night SecurityNo power after 9–10 PMCameras & lights 24×7Site secured
Peak Load HandlingDG size constrainedSmartBatt peak shavingNo load shedding
Emissions62 KVA × 13 hrs/daySignificantly reduced~3.5 T CO₂ over 6 months

Impact Delivered

Commercial Impact

The shift from a 62 KVA DG at 12–14 hours to a 30 KVA DG at 10 hours — combined with the SmartBatt monthly rental — resulted in a total monthly energy spend approximately 15–20% lower than the prior arrangement, while delivering continuous 24×7 power vs. the previous 12–14 hour window. A smaller DG attracts roughly half the monthly rental of a 62 KVA unit; lower utilisation also means less fuel per hour. The SmartBatt charge, set against these combined savings, produced positive net economics from day one.

Environmental Impact

Prior: 62 KVA × 4 L/hr × 13 hrs/day = ~52 L/day

New: 30 KVA × 3 L/hr × 10 hrs/day = ~30 L/day

Diesel avoided: ~22 L/day × 30 days = ~220 L/month

CO₂ factor: 1 litre ≈ 2.68 kg → ~590 kg CO₂/month

Over 6 months: ~3,540 kg CO₂ not emitted (≈ 3.5 tonnes)

Equivalent to taking a mid-size petrol car off the road for approximately 6 months. Beyond CO₂, reduced DG runtime also cut PM2.5, NOx, and SO₂ in an occupied working environment.

Operational Impact

  • 24×7 power continuity — site moved from a fixed 12–14 hour window to uninterrupted round-the-clock availability
  • Security restored — CCTV cameras and perimeter lighting ran through the night, eliminating the overnight blind spot
  • Peak load managed without oversizing — mid-afternoon AC loads absorbed by SmartBatt; no need to return to a larger DG
  • Reduced generator wear — DG now runs 10 hrs/day vs. 12–14 hrs, extending service intervals
  • Outdoor installation, no shelter needed — IP65 rating meant the unit could be mounted in the open alongside the DG without any enclosure
  • Quieter site environment — 15 hours of DG-off overnight operation reduced noise and diesel exhaust for on-site personnel